Week of October 23

We continued to frame our exterior walls. We are almost finished with those.


Week of October 16

We continued to frame the exterior walls.
Week of October 9, 2006


We continued to layout and build our walls at school. At the end of the week all of long, 34' walls have been built in smaller pieces and the window and door framing framing were also built and installed. Phil, a new mentor for this year was out with us again.


Laying out the walls.













The long exterior walls.






Saturday, 10/14
CW starting on the left. Mrs. Seymore, Lisa, Katie, and Meera decide colors, finishes, and floor covering for the house.

Week of October 2-6, 2006

This week at school we started to frame the exterior walls of our house . All of the framing material is provided by the Contract Lumber Company. Once we build the walls, the Righter Company will send a large "low-boy" trailer out and will transport the walls to site for us. We have two of the four longest walls framed excluding the window framing which we will do starting on Tuesday.